There are two types of contracts for the major works project – a ‘design and build’ contract for Blashford tower, and a ‘build-only’ contract for Bray, Burnham, Dorney and Taplow towers.
Blashford has a different contract type because the structure of the building is different to the other four tower blocks. We need to better understand the building so that we find the best approach to the construction work with the support of a contractor.
The works at all the tower blocks are expected to be completed in spring 2025.
Timeline for the ‘design and build’ project at Blashford
Blashford major works contractor appointment report
Blashford - Progress in 2023 and estimated timelines for 2024
For Blashford tower, the works delivery programme has been shared with residents and includes their feedback and suggestions where possible. The installation work is more complex and more intrusive than at the other towers.
To summarise progress throughout 2023:
- The site setup began in March 2023 and was mostly completed by the end of 2023
- All required final intrusive surveys, test installations, and testing construction methods on the building have been completed to finalise design and progress manufacturing
- The respite lounge for residents has been in place since December 2023 (and opened to residents from February 2024)
- The brickwork and construction work to the basement started in November 2023
The estimated completion timescales for 2024 are summarised below:
- The installation works to flats and façade take place from 22 January 2024, progressing from the bottom up, four floors at a time
- Roof work and replacements is scheduled from March to October 2024
- The window installation and cladding installation should be completed by the end of 2024
- Works completion and site demobilisation is expected in spring 2025
Timeline for the ‘build-only’ project at Bray, Burnham, Dorney and Taplow
Bray, Burnham, Dorney and Taplow contractor recommendation report (Part 1)
Bray & Taplow Towers - Progress in 2023 and estimated timelines for 2024
To summarise progress throughout 2023:
- All façade preparation work is completed, and cladding rails installed
- The roof works are completed for both towers
- The Building Maintenance Unit is installed at both towers
- Window installations are completed in about 80% of homes in each of the two towers (close to 85% at Bray and just over 75% at Taplow)
- The individual window replacement approach allows flexibility in accommodating residents’ availabilities to carry out the works in their homes
- The scaffold has started to come down since 25 September at Bray tower and since 13 November 2023 at Taplow tower
- The cladding system is fully installed to the top of the towers all the way down to floor 18 at Bray tower and floor 20 at Taplow tower
The estimated completion timescales for 2024 are summarised below:
- Window installations above the bricked area in Bray tower are expected to be completed in March 2024 and in Taplow tower in May 2024, subject to access into homes
- The insulation and cladding panels continue to be installed to the outside of both buildings and should be completed in May 2024
- The new brickworks to ground and 1st floors will be built aligned with the new cladding installed
- Works completion and demobilisation is expected in July 2024
- It must be noted that the site cabins on the forecourt of Bray will remain until the end of the project in early 2025
Burnham & Dorney Towers – Progress in 2023 and estimated timelines for 2024
To summarise progress throughout 2023:
- The scaffold building started in May 2023 and was completed at both towers in November 2023
- Brickwork removal for the ground and first floors took place at both towers in October and November 2023
- The telecommunications equipment on Dorney tower was replaced and relocated in December 2023
- The window replacements for the lower part of the buildings began on 28 September, with close to 40 homes having new windows installed. An anticipated increased pace is expected from February 2024.
- Roof works and replacement have been progressing since November 2023
The estimated completion timescales for 2024 are summarised below:
- The roof replacement and Building Maintenance Unit are being installed from January to April 2024
- As mentioned above, window replacement will progress at greater pace from February 2024 with expected completion in October 2024, subject to access into homes
- The scaffolding should start to come down in April 2024
- Works completion and demobilisation is expected in December 2024